Building for READ Foundation Middle School, Pothi, District Bhimber, AJK

| SALIENT FEATURES | |
| Location Coordinates | Latitude: 32.980760°, Longitude: 74.033304° |
| Covered Area | 8,883 sft |
| Classrooms | 16 |
| Offices | 3 |
| Toilets | 14 |
| Project Start Date | October 1, 2020 |
| Project End Date | April 5, 2022 |
| Activity # | Description | Status | Planned Month | Actual Month |
| 1 | Mobilization | Done | Oct-20 | Oct-20 |
| 2 | Layout of building | Done | Oct-20 | Oct-20 |
| 3 | Excavation for foundations | Done | Oct-20 | Oct-20 |
| 4 | RCC work in foundations | Done | Nov-20 | Nov-20 |
| 5 | Brick masonry in foundations & plinth | Done | Nov-20 | Dec-20 |
| 6 | Backfilling in foundations | Done | Dec-20 | Jan-21 |
| 7 | Plinth Beams Band | Done | Dec-20 | Jan-21 |
| 8 | Backfilling under floors | Done | Jan-21 | Feb-21 |
| 9 | Brick masonry upto Lintel level – G. Floor | Done | Jan-21 | Feb-21 |
| 10 | RCC work upto Lintel Beam- G. Floor | Done | Feb-21 | Feb-21 |
| 11 | Brick masonry upto Ceiling Level- G. Floor | Done | Feb-21 | Mar-21 |
| 12 | RCC work upto Ceiling Level- G. Floor | Done | Feb-21 | Mar-21 |
| 13 | RCC work (beams, stair, slab)- G. Floor | Done | Mar-21 | Oct-22 |
| 14 | Brick Masonry upto Lintel Beam– F. Floor | Done | Mar-21 | Oct-22 |
| 15 | RCC work upto Lintel Beam – F. Floor | Done | Apr-21 | Oct-22 |
| 16 | Brick Masonry upto Ceiling Level- F. Floor | Done | Apr-21 | Oct-22 |
| 17 | RCC Work (Beams, stair, Slab)– F. Floor | Done | May-21 | Oct-22 |
| 18 | Brick Masonry upto Lintel Beam– S. Floor | Done | Jun-21 | Oct-22 |
| 19 | Internal Plaster – G. Floor | Done | Jun-21 | Oct-22 |
| 20 | RCC work upto Lintel Beam – S. Floor | Done | Jul-21 | Oct-22 |
| 21 | Brick Masonry upto Ceiling Level- S. Floor | Done | Aug-21 | Oct-22 |
| 22 | RCC work upto Ceiling Level – S. Floor | Done | Aug-21 | Oct-22 |
| 23 | RCC Work (roof beam, stair, Slab)-S. Floor | Done | Sep-21 | Oct-22 |
| 24 | Internal Plaster – F. Floor | Done | Oct-21 | Oct-22 |
| 25 | Brick Masonry (Mumty & Parapet wall) | Done | Nov-21 | Oct-22 |
| 26 | RCC work (Columns, beams, Stair & Slab)-Mumty | Done | Nov-21 | Oct-22 |
| 27 | External Plaster | Done | Dec-21 | Oct-22 |
| 28 | Internal Plaster – S. Floor & Mumty | Done | Jan-22 | Oct-22 |
| 29 | Fixing of Electrical fixtures | Done | Jan-22 | Oct-22 |
| 30 | Sanitary works | Done | Jan-22 | Oct-22 |
| 31 | Floor Finishing- All Floors | Done | Feb-22 | Oct-22 |
| 32 | Fixing of Doors & Windows- All floors | Done | Feb-22 | Oct-22 |
| 33 | Paint work | Done | Mar-22 | Oct-22 |
| 34 | Boundary Wall | Done | Mar-22 | Oct-22 |
| 35 | Landscaping & Miscellaneous Works | Done | Mar-22 | Oct-22 |
| 36 | Handover | Done | Apr-22 | Oct-22 |
————————————————————————————————————————-






——————————————————————————————————————————————————————————–