Building for READ Foundation Middle School, Pothi, District Bhimber, AJK

SALIENT FEATURES
Location Coordinates Latitude: 32.980760°, Longitude: 74.033304°
Covered Area 8,883 sft
Classrooms 16
Offices 3
Toilets 14
Project Start Date October 1, 2020
Project End Date April 5, 2022
Activity # Description Status Planned Month Actual Month
1 Mobilization Done Oct-20 Oct-20
2 Layout of building Done Oct-20 Oct-20
3 Excavation for foundations Done Oct-20 Oct-20
4 RCC work in foundations Done Nov-20 Nov-20
5 Brick masonry in foundations & plinth Done Nov-20 Dec-20
6 Backfilling in foundations Done Dec-20 Jan-21
7 Plinth Beams Band Done Dec-20 Jan-21
8 Backfilling under floors Done Jan-21 Feb-21
9 Brick masonry upto Lintel level – G. Floor Done Jan-21 Feb-21
10 RCC work upto Lintel Beam- G. Floor Done Feb-21 Feb-21
11 Brick masonry upto Ceiling Level- G. Floor Done Feb-21 Mar-21
12 RCC work upto Ceiling Level- G. Floor Done Feb-21 Mar-21
13 RCC work (beams, stair, slab)- G. Floor  Done Mar-21 Oct-22
14 Brick Masonry upto Lintel Beam– F. Floor  Done Mar-21 Oct-22
15 RCC work upto Lintel Beam – F. Floor  Done Apr-21 Oct-22
16 Brick Masonry upto Ceiling Level- F. Floor  Done Apr-21 Oct-22
17 RCC Work (Beams, stair, Slab)– F. Floor  Done May-21 Oct-22
18 Brick Masonry upto Lintel Beam– S. Floor  Done Jun-21 Oct-22
19 Internal Plaster – G. Floor  Done Jun-21 Oct-22
20 RCC work upto Lintel Beam – S. Floor  Done Jul-21 Oct-22
21 Brick Masonry upto Ceiling Level- S. Floor  Done Aug-21 Oct-22
22 RCC work upto Ceiling Level – S. Floor  Done Aug-21 Oct-22
23 RCC Work (roof beam, stair, Slab)-S. Floor  Done Sep-21 Oct-22
24 Internal Plaster – F. Floor  Done Oct-21 Oct-22
25 Brick Masonry (Mumty & Parapet wall)  Done Nov-21 Oct-22
26 RCC work (Columns, beams, Stair & Slab)-Mumty  Done Nov-21 Oct-22
27 External Plaster  Done Dec-21 Oct-22
28 Internal Plaster – S. Floor & Mumty  Done Jan-22 Oct-22
29 Fixing of Electrical fixtures  Done Jan-22 Oct-22
30 Sanitary works  Done Jan-22 Oct-22
31 Floor Finishing- All Floors  Done Feb-22 Oct-22
32 Fixing of Doors & Windows- All floors  Done Feb-22 Oct-22
33 Paint work  Done Mar-22 Oct-22
34 Boundary Wall  Done Mar-22 Oct-22
35 Landscaping & Miscellaneous Works  Done Mar-22 Oct-22
36 Handover  Done Apr-22 Oct-22

————————————————————————————————————————-

Shuttering and steel fixing for the ground floor roof slab in progress– March 25, 2021
Shuttering and steel fixing for the ground floor roof slab in progress– March 25, 2021
Shuttering and steel fixing for the ground floor roof slab in progress– March 25, 2021
Shuttering and steel fixing for the ground floor roof slab in progress– March 24, 2021
Shuttering and steel fixing for the ground floor roof slab in progress– March 24, 2021
Masonry works of Ground floor and boundary wall in progress– February 25, 2021

 

——————————————————————————————————————————————————————————–

Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020