Building for READ Foundation Middle School, Pothi, District Bhimber, AJK

SALIENT FEATURES
Location Coordinates Latitude: 32.980760°, Longitude: 74.033304°
Covered Area 8,883 sft
Classrooms 16
Offices 3
Toilets 14
Project Start Date October 1, 2020
Project End Date April 5, 2022
Activity # Description Status Planned Month Actual Month
1 Mobilization Done Oct-20 Oct-20
2 Layout of building Done Oct-20 Oct-20
3 Excavation for foundations Done Oct-20 Oct-20
4 RCC work in foundations Done Nov-20 Nov-20
5 Brick masonry in foundations & plinth Done Nov-20 Dec-20
6 Backfilling in foundations Done Dec-20 Jan-21
7 Plinth Beams Band Done Dec-20 Jan-21
8 Backfilling under floors Done Jan-21 Feb-21
9 Brick masonry upto Lintel level – G. Floor Done Jan-21 Feb-21
10 RCC work upto Lintel Beam- G. Floor Done Feb-21 Feb-21
11 Brick masonry upto Ceiling Level- G. Floor Done Feb-21 Mar-21
12 RCC work upto Ceiling Level- G. Floor Done Feb-21 Mar-21
13 RCC work (beams, stair, slab)- G. Floor Mar-21
14 Brick Masonry upto Lintel Beam– F. Floor Mar-21
15 RCC work upto Lintel Beam – F. Floor Apr-21
16 Brick Masonry upto Ceiling Level- F. Floor Apr-21
17 RCC Work (Beams, stair, Slab)– F. Floor May-21
18 Brick Masonry upto Lintel Beam– S. Floor Jun-21
19 Internal Plaster – G. Floor Jun-21
20 RCC work upto Lintel Beam – S. Floor Jul-21
21 Brick Masonry upto Ceiling Level- S. Floor Aug-21
22 RCC work upto Ceiling Level – S. Floor Aug-21
23 RCC Work (roof beam, stair, Slab)-S. Floor Sep-21
24 Internal Plaster – F. Floor Oct-21
25 Brick Masonry (Mumty & Parapet wall) Nov-21
26 RCC work (Columns, beams, Stair & Slab)-Mumty Nov-21
27 External Plaster Dec-21
28 Internal Plaster – S. Floor & Mumty Jan-22
29 Fixing of Electrical fixtures Jan-22
30 Sanitary works Jan-22
31 Floor Finishing- All Floors Feb-22
32 Fixing of Doors & Windows- All floors Feb-22
33 Paint work Mar-22
34 Boundary Wall Mar-22
35 Landscaping & Miscellaneous Works Mar-22
36 Handover Apr-22

————————————————————————————————————————-

Shuttering and steel fixing for the ground floor roof slab in progress– March 25, 2021
Shuttering and steel fixing for the ground floor roof slab in progress– March 25, 2021
Shuttering and steel fixing for the ground floor roof slab in progress– March 25, 2021
Shuttering and steel fixing for the ground floor roof slab in progress– March 24, 2021
Shuttering and steel fixing for the ground floor roof slab in progress– March 24, 2021
Masonry works of Ground floor and boundary wall in progress– February 25, 2021

 

——————————————————————————————————————————————————————————–

Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020
Brick masonry in foundations and plinth completed– December 31, 2020